Question: ________ is a consequence of poor project management. Question content area bottom Part 1 A. Failure to obtain anticipated benefits B. Database utilization C. Training
________ is a consequence of poor project management. Question content area bottom Part 1 A. Failure to obtain anticipated benefits B. Database utilization C. Training D. Conducting a feasibility study E. Scope