Question: ___ is a structured approach for organizing all the project work and deliverables into logical groupings and subdividing them into more manageable components to help

___ is a structured approach for organizing all the project work and deliverables into logical groupings and subdividing them into more manageable components to help ensure that all the work and deliverables to complete the project are identified and included in the baseline project plan. Question 1 options: Assigning responsibilities in a responsibility assignment matrix Obtaining agreement for the project scope document Creating a work breakdown structure Finalizing the project quality plan