Question: __________ is NOT a necessary component to achieve the full potential of the lean systems concept for a manufacturer. ANSWER Unselected Short setups Unselected Frequent,

__________ is NOT a necessary component to achieve the full potential of the lean systems concept for a manufacturer. ANSWER Unselected Short setups Unselected Frequent, reliable supplies of materials Unselected A stable master production schedule Unselected Kanban