Question: Is the following statement true or false? A liquidated damages clause will be enforced if , at the time of creating the contract, it was
Is the following statement true or false? A liquidated damages clause will be enforced if at the time of creating the contract, it was very difficult to estimate actual damages and the liquidated amount is reasonable. True False