Question: Issue # 1 . The doors and windows you ordered from Marcel s Building supply were scheduled to arrive on 2 December 2 0 1

Issue #1. The doors and windows you ordered from Marcels Building supply were scheduled to arrive on 2 December 2016. Marcels Building Supply just informed you that the windows would be delayed one week and agrees to pay five days of liquidated damages in accordance with materials contract. According to the schedule, you only have three days of float before the entire project will be delayed. Another supplier, Clower Products, can get the windows and doors to you in four days after they receive your order. What do you do?