Question: It excuses contractual performance if some future event takes place. It must take place before a contracting party has a duty to perform. When the
It excuses contractual performance if some future event takes place.
It must take place before a contracting party has a duty to perform.
When the conditions of performance of a contract are decided by courts, a common decision can be that the parties to the contract have a simultaneous duty to perform. This results in:
the drafting of a new contract with express conditions of performance.
a concurrent condition of performance.
a lack of contractual performance.
an implied performance.