Question: It is good practice to have the resources responsible for completing the work to assist with the cost andPart 2 : General Multiple Choice A
It is good practice to have the resources responsible for completing the work to assist with the cost andPart : General Multiple Choice
A project is
a Temporary
b Ongoing
c Unique
d Both A and
A is a hierarchical decomposition of the project work scope into work packages that produce
the project deliverables.
a Statement of work
b Project scope document
c Network diagram
d Work breakdown structure
What range of I indicates that a project is currently experiencing a cost overrun over budget
aI
bI
cI
d None of the above
Earned Value, the value of
is a key parameter that must be determined throughout the
project.
a The work scheduled
b The resources used
c The resources assigned
d The work actually performed
A method for calculating the estimate at completion assumes that the work to be performed on the
remaining portion of the project or work package will be done at the same rate of efficiency as the work
performed so far. If the cost performance index is greater than then:
a The EAC is greater than the BAC
b The EAC is less than the BAC
c The FCAC cannot be calculated with the CPI
Which of the following is NOT an example of a risk response to a threat negative impact:
a Risk acceptance
b Risk mitigation
c Risk enhancement
d Risk avoidance
duration estimates.
a True
b False
There can be situations where the project objective needs to be modified as the project proceeds.
a True
b False
Our duration and cost estimates should be aggressive and unrealistic to help our proposal win or project
get approved.
a True
b False
A project charter should include a detailed schedule and cost estimate.
a True
b False
If the total project float is zero activities on the path do not need to be accelerated but cannot be
delayed.
a True
b False
A program comprises of related projects that are managed in a coordinated manner to obtain benefits
which are not usually available from managing them individually.
a True
b False
Project lifecycle phases are all done sequentially with no overlap between then.
a True
b False
Estimating activity costs, durations, and resources are all processes done during the executing phase.
a True
b False
Once a project begins, it must be carried through until the entire project scope is complete.
a True
b False
"Pouring concrete" and "waiting for concrete to cure" are both examples of activities.
a True
b False
Resourcelimited scheduling will sometimes cause the project's duration to be extended.
a True
b False
A Request for Quote RFQ should be used when the customer is not sure what they need.
a True
b False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock