Question: It is proposed to construct a new bridge across a river near Pondicherry. The soil deposit of the river bed is fully saturated with saturated
It is proposed to construct a new bridge across a river near Pondicherry. The soil
deposit of the river bed is fully saturated with saturated unit weight of
The nearby fault system in Bay of Bengal could generate a peak horizontal
acceleration, amax of at the site. Caissons are used as the bridge foundation.
The bottom of the caissons is at a depth of below the riverbed.
The CPT tests were carried out at the above site. At the depth of below the
ground, the penetration resistance at the cone tip and the sleeve were measured to be
MPa and kPa respectively.
During the design earthquake of magnitude will the saturated soil located at the
bottom of the caisson be liquefied?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock