Product X: It is week 1 and there are currently 20 units in stock. We need 300
Fantastic news! We've Found the answer you've been seeking!
Question:
Product X: It is week 1 and there are currently 20 units in stock. We need 300 units at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 each. Product X has a lead time of 1 week. When and how large of an order should be placed to meet the requirement of 300?
A) Week 1, 300 units
B) Week 1, 40 units
C) Week 5, 40 units
D) Week 4, 40 units
E) Week 4, 300 units
Week | 1 | 2 | 3 | 4 | 5 |
Gross requiremnts (start of period) | |||||
Schedule recipts (start of period) | |||||
Projected on hand (start of period) | |||||
Net requirements | |||||
planned order receipts | |||||
planned order releases |