Question: IT PROJECT MANAGEMENT:EX 2.4 You have a project to be completed in 12 months, and the budget of the project is R100, 000. 6 months
IT PROJECT MANAGEMENT:EX
2.4 You have a project to be completed in 12 months, and the budget of the project is R100, 000. 6 months have passed, and R60, 000 has been spent., but on closer view you find that only 40% of work has been completed so far.
Given in question :
Actual cost (AC) =R60 000
Earned Value (EV) =40% of R100 000
=R40 000
Find the project's cost varience (CV) and determine if you are under budget or over budget. (10 marks)