Question: It takes an operator 0 . 0 3 8 h to load a machine and 0 . 0 1 5 h to walk to the

It takes an operator 0.038 h to load a machine and 0.015 h to walk to the next machine. Each machine runs automatically for 0.164 h. With an operator rate of $12.80/h and a machine rate of $14/h, calculate the following:
Enter answer in the textboxes below. Enter only numerical values in the text boxes and round to 2 decimal places. Attach spreadsheet showing your complete work in the file response question ie. question #4.
a) The optimum number of machines the operator can be assigned (round to 2 decimal places)[Opt]
b) The total expected cost in dollars per unit of production for one machine when the operated is assigned the optimum number of machines rounded down.[TECDOWN]
c) The total expected cost in dollars per unit of production for one machine when the operated is assigned the optimum number of machines rounded up.[TECUP]
d) What is the preferred number of machines per operator

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!