Question: It takes an operator 0 . 0 3 8 h to load a machine and 0 . 0 1 5 h to walk to the
It takes an operator h to load a machine and h to walk to the next machine. Each machine runs automatically for h With an operator rate of $h and a machine rate of $h calculate the following:
Enter answer in the textboxes below. Enter only numerical values in the text boxes and round to decimal places. Attach spreadsheet showing your complete work in the file response question ie question #
a The optimum number of machines the operator can be assigned round to decimal placesOpt
b The total expected cost in dollars per unit of production for one machine when the operated is assigned the optimum number of machines rounded down.TECDOWN
c The total expected cost in dollars per unit of production for one machine when the operated is assigned the optimum number of machines rounded upTECUP
d What is the preferred number of machines per operator
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock