Question: It takes Boeing 2 9 , 4 5 4 hours to produce the eighth 7 8 7 jet. The learning factor is 8 0 %
It takes Boeing hours to produce the eighth jet. The learning factor is
Time required for the production of the twelfth :
th unit time
hours
round your response to the nearest whole number