Question: It the standard quantity (SQ), actual quantity (AQ), standard price (SP), and actual price (AP) are 350 units, 400 units, $12, and $13 respectively,

\ It the standard quantity (SQ), actual quantity (AQ), standard price (SP), and actual price (AP) are 350 units, 400 units, $12, and $13 respectively, then the total budget variance is A. $1000 Favorable B. $250 Favorable C. $250 Unfavorable D. $1,000 Unfavorable