Question: ITEC 3 7 0 6 : Software Engineering Project Management Assignment 3 ( worth 1 0 % ) You have been asked to lead a
ITEC: Software Engineering Project Management
Assignment worth
You have been asked to lead a Crystal corporation a software company session to determine the requirements for a new project. You must develop a specific schedule for the tasks listed below. All durations are in days.
Show all your work.
Taskactivity Predecessor Node Successor Node Estimated Duration
A Contact participants and explain their roles Null B
B Arrange meeting room A CD
C Prepare agenda B E
D Prepare information packets B F
E Create visual aids C F
F Send emails to participants DE G
G Conduct JAD session F Null
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
June June June June June June June
June June June July July July July
July July July July July July July
July July July July July July July
July July July July July July July
a On the next page, draw a network diagram representing the schedule. The project starts on June
marks for correct PDM format content letter dates, duration
for correct sequence
for correct dates
b Identify all the paths on the diagram and document how long each one is marks
c What is the critical path for this project and how long is it mark
d What is the end date for the project? mark
e Identify an activity that has a burst. mark B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock