The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 8
B A 3
C A 7
D C 3
E B%media:cm.png% D 4
F D 3
G E%media:cm.png% F 6
What is the critical path?
multiple choice
A-C-D-E-G
A-B-E-G
A-B-D-F-G
A-C-D-F-G
How many weeks will it take to complete the project?
How much slack does activity B have?