The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D C
E Bmedia:cmpng D
F D
G Emedia:cmpng F
What is the critical path?
multiple choice
ACDEG
ABEG
ABDFG
ACDFG
How many weeks will it take to complete the project?
How much slack does activity B have?