Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1,2,3,4.
Job Work Center/Machine Hours Due Date (days)
1 A/3, B/2, C/23
2 C/2, A/42
3 B/6, A/1, C/34
4 C/4, A/1, B/23
a. What is the makespan?
b. How much machine idle time is there?
c. When is each job delivered compared with its due date?
d. How much idle time (waiting time) is there for each job?
e. Devise a better job sequence for processing.
Sequence Job
1 multiple choice 1
1
2
3 Correct
4
2 multiple choice 2
1
2
3
4
3 multiple choice 3
1
2
3
4
4 multiple choice 4
1
2
3
4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!