Question: Item: 2 Pneumatic control valve Order Policy: 7 5 units Lead Time: 1 week Quantity on Hand: 1 0 Week 1 2 3 4

Item: 2" Pneumatic control valve
Order Policy: 75 units
Lead Time: 1 week
Quantity
on Hand: 10
Week
1
2
3
4
5
6
7
8
Forecast
40
50
45
40
25
30
50
50
Customer orders(booked)
60
40
25
35
10
10
15
0
Projected on-hand inventory
MPS quanity