A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown, do the following:
Job Job Time Days Due Date
a
b
c
d
e
f
a Determine the processing sequence using First come, first served, Shortest processing time, Earliest due date. The list is in First come, first served order.
a For each sequence, compute the average job tardiness, the average flow time. Round your intermediate calculations and final answers to decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock