Question: Item: A Safety Stock = 200 Description: Eiger Backpack Lot-Size = LFL Lead Time = 2 weeks Period 37 38 39 40 41 42 43

Item: A Safety Stock = 200

Description: Eiger Backpack Lot-Size = LFL Lead Time = 2 weeks

Period

37

38

39

40

41

42

43

44

Gross Requirements

780

830

850

900

920

950

950

950

Scheduled Receipts

0

1200

0

0

0

0

0

0

On Hand

2400

Net Requirements

Planned Order Receipts

Planned Order Releases

X