Question: Item2 10points References Check my workCheck My Work button is now enabled Item 2 Colby Limited is a manufacturing company whose total factory overhead costs
Item2
10points
References
Check my workCheck My Work button is now enabled
Item 2
Colby Limited is a manufacturing company whose total factory overhead costs fluctuate somewhat from year to year, according to the number of machine-hours worked in its production facility. These costs at high and low levels of activity over recent years are given below:
| Level of Activity | ||||||
| Low | High | |||||
| Machine-hours | 68,200 | 98,200 | ||||
| Total factory overhead costs | $ | 39,091,200 | $ | 47,071,200 | ||
The factory overhead costs above consist of indirect materials, rent, and maintenance. The company has analyzed these costs at the 68,200 machine-hours level of activity as follows:
| Indirect materials (variable) | $ | 12,617,000 |
| Rent (fixed) | 16,700,000 | |
| Maintenance (mixed) | 9,774,200 | |
| Total factory overhead costs | $ | 39,091,200 |
For planning purposes, the company wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the factory overhead cost of $47,071,200 at the high level of activity consists of maintenance cost.
2. Using the highlow method, estimate a cost formula for maintenance.
3. What total overhead costs would you expect the company to incur at an operating level of 73,200 machine-hours?
Step by Step Solution
There are 3 Steps involved in it