Question: ITPM One of the project management process groups is Select one: O a. sending O b. initiating O c. transferring O d. combining Each box

ITPM
One of the project management process groups is Select one: O a. sending O b. initiating O c. transferring O d. combining Each box is an activity, the number it contains is the duration of the activity in days. How many day/s can we delay activity B without affecting the finish day for the project. A B W 2 Select one: a. 5 days b. 0 day. c. 6 days d. 4 days