Question: it's a small assignment Quiz: Chapter 15 Quiz Question 3 of 4 This quiz: 4 point(s) possible This question: 1 point(s) possible SO () First


it's a small assignment
Quiz: Chapter 15 Quiz Question 3 of 4 This quiz: 4 point(s) possible This question: 1 point(s) possible SO () First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Day Job 1 2 3 4 5 6 7 8 9 10 11 0 0 3 Job D was scheduled to begin early on day 3 and take 6.5 days. As of now (the review point after day 4), it is 2 days ahead of schedule. Job E should begin on day 1 and take 4 days. It was on time. Job F was to begin on day 4, but maintenance forced a delay of 1.0 day. The job should now take 5 full days. It is now on schedule. Job G is a day behind schedule. It started at the beginning of day 2 and should require 7 days to complete. Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks. D E F 7 G Now Quiz: Chapter 15 Quiz Question 4 of 4 This quiz: 4 point(s) possible This question: 1 point(s) possible First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Day Job 1 2 3 4 5 6 7 8 9 10 11 Job D was scheduled to begin early on day 2 and take 7.5 days. It started on time and as of now (the review point after day 4), it is 2 days ahead of schedule. Job E should begin on day 1 and take 3 days. It was on time. Job F was to begin on day 3, but maintenance forced a delay of 1.5 days. The job should now take 5 full days. It is now on schedule. Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to complete. D Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of the dashed line provided for each of the tasks. E F G 11 NowStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
