Question: it's not C Two methods are used to predict how many customers will call in for help in the next four days. The first method
it's not C
Two methods are used to predict how many customers will call in for help in the next four days. The first method predicts the numbers of callers to be 23 , 5,14 , and 20 for the four respective days. The second method predicts 20 , 13,14 , and 20 for the four respective days. The actual numbers of callers turn out to be 23,10,15, and 19 . Which method has the smaller mean absolute error (MAE)? Cannot be determined The second meth Both methods have the same MAE