Question: Ivanhoe Construction is constructing an office building under contract for Cannon Company and uses the percentage - of - completion method. The contract calls for

Ivanhoe Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $900000 each quarter. The total contract price is $18898000 and Ivanhoe estimates total costs of $18100000. Ivanhoe estimates that the building will take 3 years to complete and commences construction on January 2,2024. At December 31,2024, Seasons estimates that it is 30% complete with the construction, based on costs incurred.
By December 31,2025,"Ivanhoe estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18700000 due to unanticipated price increases. What is the total amount of Construction Expenses that Ivanhoe will recognize for the year ended December 31,2025?
$8595000
$7905600
$14025000
$8355600
 Ivanhoe Construction is constructing an office building under contract for Cannon

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!