Question: Jabez Contractors installs network routers. Using the CPM method and in reference to the table provided comment on the expected completion time of the project
Jabez Contractors installs network routers. Using the CPM method and in reference to the table provided comment on the expected completion time of the project and identify the activities that need to be prioritised by the project manager. (No diagram is required) Table 1: Project Installation
|
Activity
|
Predecessor |
Optimistic |
Most likely |
Pessimistic |
Estimated time |
| A | - | 4 | 7 | 10 | 7 |
| B | - | 2 | 9 | 10 | 8 |
| C | A, B | 2 | 5 | 8 | 5 |
| D | C | 16 | 19 | 28 | 20 |
| E | C | 6 | 9 | 24 | 11 |
| F | E | 1 | 7 | 13 | 7 |
| G | C | 4 | 10 | 28 | 12 |
| H | D, F | 2 | 5 | 14 | 6 |
| I | G | 5 | 8 | 17 | 9 |
| J | H, I | 2 | 5 | 8 | 5 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock