Question: Jack had a contract with Greg to make a custom suit for Greg. The suit would be picked up on March 1 7 th and
Jack had a contract with Greg to make a custom suit for Greg. The suit would be picked up on March th and Greg would pay $ for the suit that day. On March th Jack completed the suit for Greg. On March th Greg called Jack and informed him that he no longer wanted the suit and that he would not pay for it
What is the earliest date Jack can sue Greg?
Group of answer choices
March th
March th
March th
March th
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!