Question: Jack had a contract with Greg to make a custom suit for Greg. The suit would be picked up on March 1 7 th and

Jack had a contract with Greg to make a custom suit for Greg. The suit would be picked up on March 17th and Greg would pay $200 for the suit that day. On March 9th, Jack completed the suit for Greg. On March 11th, Greg called Jack and informed him that he no longer wanted the suit and that he would not pay for it.
What is the earliest date Jack can sue Greg?
Group of answer choices
March 17th
March 18th
March 12th
March 11th