Jack Palmer, head of the Special Projects Division for Ramstein Products, had been in his new...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Jack Palmer, head of the Special Projects Division for Ramstein Products, had been in his new position for only three months when he ordered an evaluation of project management practices within his division. Ramstein Products is a leading developer of integrated testing equipment for the energy industry, marketing more than 45 product lines to a variety of organizations involved in natural gas and oil exploration, power generation, and utilities. As head of special products, Jack was responsible for an ongoing project portfolio of 50 to 60 new product development projects. Top management at Ramstein estimated that 60% of company revenue came from new products and took a keen interest in the operations of the Special Projects Division. As part of the evaluation, Jack became aware of the troubling fact that projects were routinely overrunning their budget and schedule targets, often by a significant margin. This fact was particularly troubling because Jack, who had once worked as a project manager within the division, understood that the project schedules were not terribly aggressive. In fact, he believed that a great deal of padding went into the project schedules a they were initially developed. Why, then, were projects chronically late and over budget? Although important to Ramstein's future success, the Special Projects Division had long been operating on a tight resource level. There were seven system integration engineers supporting a portfolio of 55 projects. These engineers were very important to Ramstein's new product development efforts, and their services were often stretched to the breaking point. One of the senior engineers, Mary, recently informed Jack that she was supporting 14 projects, all being developed at the same time! Jack reflected on some of the information he had received during his evaluation. Clearly, the easiest option would be to approach top management and request more systems integration engineers for his division. He had a hunch however that with the current economic conditions, any such request from him would probably be turned down. He needed to get a handle on the problems and apply some solutions now with the resources he had available. Questions 1. Applying Goldratt's ideas of critical resources, what is the system constraint within the Special Projects Division that is causing bottlenecks and delaying the projects? (40) 2. How is multitasking contributing to systemic delays in project development at Ramstein? (30) 3. How could the drum buffer concepts from Critical Chain Portfolio Management be applied to this problem? (30) Jack Palmer, head of the Special Projects Division for Ramstein Products, had been in his new position for only three months when he ordered an evaluation of project management practices within his division. Ramstein Products is a leading developer of integrated testing equipment for the energy industry, marketing more than 45 product lines to a variety of organizations involved in natural gas and oil exploration, power generation, and utilities. As head of special products, Jack was responsible for an ongoing project portfolio of 50 to 60 new product development projects. Top management at Ramstein estimated that 60% of company revenue came from new products and took a keen interest in the operations of the Special Projects Division. As part of the evaluation, Jack became aware of the troubling fact that projects were routinely overrunning their budget and schedule targets, often by a significant margin. This fact was particularly troubling because Jack, who had once worked as a project manager within the division, understood that the project schedules were not terribly aggressive. In fact, he believed that a great deal of padding went into the project schedules a they were initially developed. Why, then, were projects chronically late and over budget? Although important to Ramstein's future success, the Special Projects Division had long been operating on a tight resource level. There were seven system integration engineers supporting a portfolio of 55 projects. These engineers were very important to Ramstein's new product development efforts, and their services were often stretched to the breaking point. One of the senior engineers, Mary, recently informed Jack that she was supporting 14 projects, all being developed at the same time! Jack reflected on some of the information he had received during his evaluation. Clearly, the easiest option would be to approach top management and request more systems integration engineers for his division. He had a hunch however that with the current economic conditions, any such request from him would probably be turned down. He needed to get a handle on the problems and apply some solutions now with the resources he had available. Questions 1. Applying Goldratt's ideas of critical resources, what is the system constraint within the Special Projects Division that is causing bottlenecks and delaying the projects? (40) 2. How is multitasking contributing to systemic delays in project development at Ramstein? (30) 3. How could the drum buffer concepts from Critical Chain Portfolio Management be applied to this problem? (30)
Expert Answer:
Answer rating: 100% (QA)
ANSWER1 Determine the constraint in the system Determine the primary constraint Limited resources seven system integration engineers are responsible f... View the full answer
Posted Date:
Students also viewed these accounting questions
-
Qualcomm Incorporated is a leading developer and manufacturer of digital wireless telecommunications products and services. Qualcomm reported the following inventories on September 30, 2004, in the...
-
Bauer Performance Sports Ltd. is a leading developer and manufacturer of ice hockey, roller hockey, and lacrosse equipment as well as related apparel. The company holds the top market share position...
-
Bauer Performance Sports Ltd. is a leading developer and manufacturer of ice hockey, roller hockey, and lacrosse equipment as well as related apparel. Its products are marketed under the Bauer...
-
Q4. a- In a uniform electric field, what factors does the electrical potential energy depend on? b- What is the difference between APE electric and PE electric?
-
Karen Furber, a photographer, opened Gratitude in Photography on January 1, 2015. Selected transactions from the first month are below: a. Transferred cash into the business, $20,000. b. Purchased...
-
Marsh Limited has investigated the possibility of investing in a new machine. The following data have been extracted from the report relating to the project: Cost of machine on 1 January Year 6:...
-
A toroid carries a current \(I\) and has \(n\) circular windings per unit length measured along the inside edge of the windings. The radius of each circular winding is \(R_{\text {winding }}\), and...
-
Assume that Coaltown Corporation has a machine that cost $52,000, has a book value of $35,000, and has a market value of $40,000. The machine is used in Coaltowns manufacturing process. For each of...
-
1. Your program asks the user how many bananas they want to buy, and what the price is. This information is then passed to getTotal to calculate the total cost. System.out.println("How many bananas...
-
A textile company produces shirts and pants. Each shirt requires two square yards of cloth, and each pair of pants requires three square yards of cloth. During the next two months the following...
-
Identify the sustainability impacts associated with oil drilling operations such as that in the Gulf of Mexico? Despite these impacts, why is oil drilling still undertaken
-
Explain the difference between a freedom to contract and a fairness approach to enforcement. In this context, what is the significance of the Simeone case?
-
Define and distinguish among subject matter, personal, and in rem jurisdiction.
-
What is a CAFR? Discuss.
-
Define putative spouse and discuss its significance.
-
Describe the purpose of a married womens property act.
-
A stone is thrown straight down from the edge of a roof, 1025 feet above the ground, at a speed of 7 feet per second. A. Remembering that the acceleration due to gravity is -32 feet per second...
-
14. In testing the existence assertion, an auditor ordinarily works from the a. Financial statements to the accounting records. b. General journal to the general ledger. c. Supporting evidence to the...
-
True or False: Build-Operate-Transfer (BOT) makes use of a public-private partnership.
-
Do an Internet search on "build operate transfer." Identify a BOT project, preferably from your home continent (e.g., AF, AS, EU, Pacific, NA, SA), and copy a small portion of what you find (a page...
-
Using an Internet-based search on 'build operate transfer," find an additional definition from a source other than used in Section 14.2. Copy and paste it, as well as any graphics, examples,...
Study smarter with the SolutionInn App