Question: Janno Enterprises allocates overhead based on actual machine hours. Selected data for the most recent year follows. Estimated manufacturing overhead cost Actual manufacturing overhead
Janno Enterprises allocates overhead based on actual machine hours. Selected data for the most recent year follows. Estimated manufacturing overhead cost Actual manufacturing overhead cost Estimated machine hours Actual machine hours $236,000 $244,700 20,200 22,900 The estimates were made as of the beginning of the year, while the actual results were for the entire year. The amount of manufacturing overhead allocated for the year based on the predetermined overhead rate using estimated machine hours would have been ? (Round intermediary calculations to the nearest cent and final answer to the nearest dollar.) A. $215,849. B. $236,000. C. $244,700. D. $267,472. ...
Step by Step Solution
There are 3 Steps involved in it