Question: Janus Construction signs a contract to construct a small warehouse. The amount Janus will be paid depends on when the warehouse will be finished and

Janus Construction signs a contract to construct a small warehouse. The amount Janus will be paid depends on when the warehouse will be finished and is totally dependent on management's efficiency in production planning. The contract price is $100,000. Each one-week delay results in a penalty equal to $2,000. Janus's management, well-versed in scheduling this kind of job, estimates the following distribution of outcomes and associated probabilities:

On-time completion: 30% chance One-week delay: 50% chance Two-week delay: 10% chance Three-week delay: 10% chance

Under the most likely amount approach, the transaction price is:

a. $98,000.
b. $100,000.
c. $94,000.
d. $96,000.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!