Question: Janus Construction signs a contract to construct a small warehouse. The amount Janus will be paid depends on when the warehouse will be finished and
Janus Construction signs a contract to construct a small warehouse. The amount Janus will be paid depends on when the warehouse will be finished and is totally dependent on management's efficiency in production planning. The contract price is $100,000. Each one-week delay results in a penalty equal to $2,000. Janus's management, well-versed in scheduling this kind of job, estimates the following distribution of outcomes and associated probabilities:
On-time completion: 30% chance One-week delay: 50% chance Two-week delay: 10% chance Three-week delay: 10% chance
Under the most likely amount approach, the transaction price is:
| |||
| |||
| |||
|