Question: JBD company has just completed a project installing a new software system. The company is preparing a document summarising all the issues that arose during

JBD company has just completed a project installing a new software system.
The company is preparing a document summarising all the issues that arose during the project. The document will include an analysis of why the issues arose and what the team could have done to avoid them.
What document is JBD currently completing?
Solution
A.Communications plan.
B.Risk register.
C.Project budgeted.
D.Lessons learned log.