Jets Ltd. contracted to build a high-rise for $ 6,000,000. Construction began in 2020 and is expected
Fantastic news! We've Found the answer you've been seeking!
Question:
Jets Ltd. contracted to build a high-rise for $ 6,000,000. Construction began in 2020 and is expected to be completed in 2022. Data for 2020 and 2021 are:
2020 2021
Costs incurred $ 900,000 $ 1,700,000
Estimated costs to complete 3,600,000 2,400,000
Instructions
Using the percentage-of-completion method and the cost-to-cost basis,
a) How much gross profit should be reported for 2020? Show your calculation.
b) How much gross profit should be reported for 2021? Show your calculation.
c) Prepare the journal entry to record the revenue and gross profit for 2021.
Related Book For
Introduction to Mathematical Statistics and Its Applications
ISBN: 978-0321693945
5th edition
Authors: Richard J. Larsen, Morris L. Marx
Posted Date: