Jiaying's stakeholders indicate that their project must finish one week earlier than scheduled. Which tasks should she
Fantastic news! We've Found the answer you've been seeking!
Question:
Jiaying's stakeholders indicate that their project must finish one week earlier than scheduled. Which tasks should she focus on crashing in order to shorten the schedule?
1. tasks on critical path
2. tasks that are least expensive
3. tasks with lower priority