Question: JIT/ Continuous Flow / Takt time / Heijunka: LCB Enterprises produces three products using a mixed-model assembly line. This line is operated eight hours a
JIT/ Continuous Flow / Takt time / Heijunka: LCB Enterprises produces three products using a mixed-model assembly line. This line is operated eight hours a day for 250 days per year and produces 14 units per hour of all products. The forecasts of annual demand for each of the three products, codenamed John, Goldie, and Ziggy, are as follows: 16,000 units of John (J), 8,000 units of Goldie (G), and 4,000 units of Ziggy (Z). If mixed-model JIT scheduling is used, calculate the TAKT time, in minutes, of the above assembly line. How many units of each model will be produced before the production cycle is repeated? For one such production cycle, determine a satisfactory JIT production sequence of models.