Question: Job A B C D E F G Processing time 4 6 7 4 1 2 5 Deadline 20 10 6 20 2 3 30
| Job | A | B | C | D | E | F | G |
| Processing time | 4 | 6 | 7 | 4 | 1 | 2 | 5 |
| Deadline | 20 | 10 | 6 | 20 | 2 | 3 | 30 |
Schedule to:
- Minimize the maximum tardiness
- Minimize the summation of completion times
- Minimize the number of late orders
Describe the approach you used and the meaning of its outcomes.