Question: Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,300 of direct materials and used $4,800

Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,300 of direct materials and used $4,800 of direct labor. The job was not finished by the end of September, but needed an additional $3,800 of direct materials in October and additional direct labor of $7,300 to finish the job. The company applies overhead at the end of each month at a rate of 100% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October?

A. 30,300

B. 18,400

C. 23,200

D. 31,300

E. 19,200

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock