Question: Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,300 of direct materials and used $3,800

Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,300 of direct materials and used $3,800 of direct labor. The job was not finished by the end of September, but needed an additional $2,800 of direct materials in October and additional direct labor of $6,300 to finish the job. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October?