Question: JOB DATA ENTRY (HOURS) VERIFY (HOURS) A 2.4 1.7 B 3.4 2.8 C 1.6 3.2 D 2.3 0.8 Part 2 In what order should the
| JOB | DATA ENTRY (HOURS) | VERIFY (HOURS) |
| A | 2.4 | 1.7 |
| B | 3.4 | 2.8 |
| C | 1.6 | 3.2 |
| D | 2.3 | 0.8 |
Part 2
In what order should the jobs be done if the company has one operator for each job?
The order is: