Question: Job Date Job Received Due Date Duration ( days ) BR - 0 2 2 3 1 3 1 0 3 0 CX - 0

Job Date Job Received Due Date Duration (days)
BR-0223131030
CX-0122830015
DE-0622527025
RG-0523032035
SY-1123536040Using the FCFS(first come, first served) decision rule for sequencing the jobs, the order is:
Part 2Part 3Part 4Part 5
Sequence
Job
1
BR-02
2
CX-01
3
DE-06
4
RG-05
5
SY-11
Part 6
The total flow time for the sequence developed using the FCFS rule=
145 days (round your response to two decimal places).
Part 7
The percentage utilization for the sequence developed using the FCFS rule=
5.8%(enter your response as a percentage rounded to two decimal places).
Part 8
The average number of jobs in the system for the sequence developed using the FCFS rule=
29 jobs (round your response to two decimal places).
Part 9
The average tardiness(job lateness) for the sequence developed using the FCFS rule=
9 days (round your response to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!