Question: Job Process Time Due Date Start Date End Date Days Late Flow Time A 15 177 130 144 B 23 211 145 167 C 17
| Job | Process Time | Due Date | Start Date | End Date | Days Late | Flow Time |
| A | 15 | 177 | 130 | 144 | ||
| B | 23 | 211 | 145 | 167 | ||
| C | 17 | 188 | 168 | 184 | ||
| D | 14 | 219 | 185 | 198 | ||
| E | 32 | 195 | 199 | 230 |
Given the FSFS sequence information above, determine the following:
Average days late: [A] days (Round ansewr to one decimal place, if applicable.)
Utilization: [B]% (Enter answer as a percentage. Round answer to one decimal place, if applicable.)
Avg. compleation time: [C] days (Round answer to one decimal place, if applicable.)