Question: Job Process (X) manufacturing (hours) Process (Y) Installation (hours) A (Motor) 3 2 B (Transmission) 6 8 C (battery) 5 6 D (Chassis) 7 4
| Job | Process (X) manufacturing (hours) | Process (Y) Installation (hours) |
| A (Motor) | 3 | 2 |
| B (Transmission) | 6 | 8 |
| C (battery) | 5 | 6 |
| D (Chassis) | 7 | 4 |
| E (Car body) | 2 | 2 |
| F (Interior) | 4 | 3 |
(a) The above 10 jobs have just arrived. Use Johnsons rule to determine the optimal sequence to schedule the jobs. If there is more than one optimal sequence, show them all.
(b) Draw a Gantt chart for your schedule. If there is more than one optimal sequence, show anyone of them.
(c) What is the suggestion for Tesla to increase productivity?