Question: job processing time due date(Di) 1 27 37 2 30 38 3 29 40 4 20 30 5 19 43 An insurance claims work area
| job | processing time | due date(Di) |
| 1 | 27 | 37 |
| 2 | 30 | 38 |
| 3 | 29 | 40 |
| 4 | 20 | 30 |
| 5 | 19 | 43 |
An insurance claims work area has five claims waiting for processing as follows:
Use the Excel Sequencing template to find the average flowtime, average and maximum tardiness, and average lateness for the following sequences: SPT sequence, EDD sequence, and the sequence 2-1-4-3-5. Round your answers for the average values to two decimal places.
The SPT sequence is ____ - ____ - ____ - ____ - ____
Average Flow time ____
Average tardiness ____
Maximum tardiness ____
Average Lateness ____
The EDD sequence is ____ - ____ - ____ - ____ - ____
Average Flow time ____
Average tardiness ____
Maximum tardiness ____
Average Lateness ____
2-1-4-3-5 sequence
Average Flow time ____
Average tardiness ____
Maximum tardiness ____
Average Lateness ____
What sequencing rule do you recommend?
The -Select-(SPT, EDD or 2-1-4-3-5) is recommended as it minimizes average flow time and number of jobs in system.