Question: Job Processing Time (hours) Due (hours) P 20 50 Q 10 35 R 50 90 S 15 35 T 55 75 Dispatching Rule Job

Job Processing Time (hours) Due (hours) P 20 50 Q 10 35R 50 90 S 15 35 T 55 75 Dispatching Rule Job

Job Processing Time (hours) Due (hours) P 20 50 Q 10 35 R 50 90 S 15 35 T 55 75 Dispatching Rule Job Sequence SPT CR FCFS EDD MST Average Flow Average Number Time of Jobs Average Lateness