Question: Job Processing time ( hours ) Weight / Priority ( cost per hour ) A 4 4 B 5 8 C 4 7 D 6

Job Processing time (hours) Weight/Priority (cost per hour)
A 44
B 58
C 47
D 65
Assume the WSPT rule is used. Which job should be processed last?