Question: job step1 step2 due date A 7 8 23 B 4 3 15 C 6 6 34 D 3 5 16 E 7 4 27
| job | step1 | step2 | due date |
| A | 7 | 8 | 23 |
| B | 4 | 3 | 15 |
| C | 6 | 6 | 34 |
| D | 3 | 5 | 16 |
| E | 7 | 4 | 27 |
If using the earliest due date to sequence all five jobs, what is the start time of job A in the first step, and what is the average lateness for all 5 jobs?