Question: Job##Proc. time at Work Center 1 ( hours ) ##Proc. time at Work Center 2 ( hours ) table [ [ A , 1

Job##Proc. time at Work Center 1(hours)##Proc. time at Work Center 2(hours)
\table[[A,12,7],[B,6,4],[C,7,18],[D,10,2],[F,17,10]]
Six specialty jobs at a tool and die shop must be processed through two work centers (drill and lathe machine). The time for processing each job is given in the table. Determine the sequence that will minimize the total completion time for this group of jobs. What is the 3rd job in this sequence? ((c)orsdemir. Copyrighted content. Only enter the name of the job. Ex: A)