Question: Jobs A , B , C , D , and E must go through Processes Ione and II in that sequence ( Process Ione first,

Jobs A, B, C, D, and E must go through Processes Ione and II in that sequence (Process Ione first, then Process II).
JOB REQUIRED PROCESSING TIME ON Ione REQUIRED PROCESSING TIME ON II
A 45
B 1614
C 87
D 1211
E 39
Use Johnson's rule to determine the optimal sequence in which to schedule the jobs to minimize the total required time.