Question: Jobs A , B , C , D , and E must go through Processes I and II in that sequence ( Process I first,

Jobs A, B, C, D, and E must go through Processes I and II in that
sequence (Process I first, then Process II). Use Johnsons rule to
determine the optimal sequence in which to schedule the jobs to
minimize the total required time.
Job
Required
Processing
Time on I
Required
Processing
Time on II
A 45
B 1614
C 87
D 1211
E 39