Question: John agrees with Bill to construct a building for $100,000.The contract is legal and enforceable.John has finished 80% of the contract when he decides the
John agrees with Bill to construct a building for $100,000.The contract is legal and enforceable.John has finished 80% of the contract when he decides the weather is too good in Florida to miss, so he abandons the project and moves to Florida permanently.Prior to moving he had received $50,000 towards the contract price. What options does Bill have?What if it cost him $75,000 to finish the building? Can he sue to force John to finish? What are his damages?