Question: Jonczyk Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $ 404,000 , has an expected useful life of 12
Jonczyk Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $404,000, has an expected useful life of 12 years and a salvage value of zero, and is expected to increase net annual cash flows by $67,000. Project B will cost $283,000, has an expected useful life of 12 years and a salvage value of zero, and is expected to increase net annual cash flows by $49,000. A discount rate of 10% is appropriate for both projects. Click here to view PV table.
Calculate the net present value and profitability index of each project. (If the net present value is negative, use either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round present value answers to 0 decimal places, e.g. 125 and profitability index answers to 2 decimal places, e.g. 15.52. For calculation purposes, use 5 decimal places as displayed in the factor table provided, e.g. 1.25124.)
Which project should be accepted based on net present value?
Which project should be accepted based on profitability index?
Calculate the net present value and profitability index of each project. (If the net present value is negative, use either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round present value answers to 0 decimal places, e.g. 125 and profitability index answers to 2 decimal places, e.g. 15.52. For calculation purposes, use 5 decimal places as displayed in the factor table provided, e.g. 1.25124.)
| Project A | Project B | |||
|---|---|---|---|---|
| Net present value | $enter a dollar amount rounded to 0 decimal places | $enter a dollar amount rounded to 0 decimal places | ||
| Profitability index | enter the index rounded to 2 decimal places | enter the index rounded to 2 decimal places |
Which project should be accepted based on net present value?
| select a project based on its net present value Project AProject B | should be accepted. |
Which project should be accepted based on profitability index?
| select a project based on its profitability index Project BProject A | should be accepted. |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock