Question: Jordan is PM for a project to implement a comprehensive sales forecasting solution. In this project, Jordan should tailor the complexity and level of detail

Jordan is PM for a project to implement a comprehensive sales forecasting solution. In this project, Jordan should tailor the complexity and level of detail of the procurement documents to be consistent with:

b) The number of resources who will be involved in the project.

e) C & D

d)The sum of work packages as outlined by the Work Breakdown Structure (WBS).

a) The value of, and risks associated with, the planned procurement.

c) The time available to dedicate to the procurement documents.